A. crash time
B. normal time
C. optimistic time
D. standard time
Related Mcqs:
- If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is_________________?
A. 500 cum
B. 1000 cum
C. 1500 cum
D. 2000 cum - The direct cost of a project with respect to normal time is________________?
A. minimum
B. maximum
C. zero
D. infinite - Which of the following does not represent an activity?
A. site located
B. foundation is being dug
C. the office area is being cleaned
D. the invitations are being sent - The time corresponding to minimum total project cost is_______________?
A. crash time
B. normal time
C. optimistic time
D. between normal time and crash time - In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?
A. longest duration
B. highest cost slope
C. least cost slope
D. shortest duration - The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be________________?
A. Rs. 8,800/-
B. Rs. 7,600/-
C. Rs. 6,400/-
D. Rs. 5,000/- - Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
A. on commencement of work at site for payment of loan taken by him
B. for the purchase of construction materials
C. for the payment of advances to labour and other staff
D. for all activities required to start the work at site on finalization of the contract document - In time-cost optimization of a project, crashing is done____________?
A. on all the activities
B. on all the activities lying on the critical path
C. only on activities lying on the orginal critical path and having flatter cost slopes
D. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope - A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be________________?
A. Rs.1740
B. Rs.3480
C. Rs.5220
D. Rs.6960 - The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as_______________?
A. total float
B. free float
C. interfering float
D. independent float