A. Hoe
B. Shovel
C. Dragline
D. None of the above
Related Mcqs:
- If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is_________________?
A. 500 cum
B. 1000 cum
C. 1500 cum
D. 2000 cum - Which one of the following is not an excavating and moving type of equipment ?
A. Bulldozer
B. Clam shell
C. Scraper
D. Dump truck - If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be_________________?
A. equal to X
B. more than X
C. less than X
D. any of the above - An earth moving equipment costs Rs. 5,00,000/- and has an estimated life of 10 years and a salvage value of Rs. 50,000/-.What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069 ?
A. Rs. 31050
B. Rs. 34500
C. Rs. 37950
D. Rs. 50000 - The most suitable type of equipment for compaction of cohesive soils is_________________?
A. Smooth-wheeled rollers
B. Vibratory rollers
C. Sheep foot rollers
D. Tampers - The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be________________?
A. Rs. 8,800/-
B. Rs. 7,600/-
C. Rs. 6,400/-
D. Rs. 5,000/- - A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be________________?
A. Rs.1740
B. Rs.3480
C. Rs.5220
D. Rs.6960 - Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing Reason R: If the angle of swing is decreased, the cycle time will be decreased_______________?
A. Both A and R are true and R is the correct explanation of A
B. Both A and R are true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true - The time corresponding to minimum total project cost is_______________?
A. crash time
B. normal time
C. optimistic time
D. between normal time and crash time - The normal time required for the completion of project in the above problem is_______________?
A. 9 days
B. 13 days
C. 14 days
D. 19 days