A. 4 days
B. 6 days
C. 10 days
D. 16 days
Construction Planning and Management
Construction Planning and Management
A. 50%
B. 84.1%
C. 99.9%
D. 100%
A. Rs. 31050
B. Rs. 34500
C. Rs. 37950
D. Rs. 50000
A. 10000 kg
B. 12500 kg
C. 22500 kg
D. 5000 kg
A. 30 kg
B. 300 kg
C. 900 kg
D. 1000 kg
(i) Vehicle load
(ii) Grade
(iii) Ground
select the correct statements?
A. only (i) is correct
B. (i) and (ii) are correct
C. (i) and (iii) are correct
D. (ii) and (iii) are correct
A. 500 cum
B. 1000 cum
C. 1500 cum
D. 2000 cum
A. Rs. 4,75,000/-
B. Rs. 5,75,000/-
C. Rs. 6,50,000/-
D. Rs. 8,50,000/-
A. equal to X
B. more than X
C. less than X
D. any of the above
(i) Output can be increased by reducing the angle of swing for a given depth of cut
(ii) For a given angle of swing, output will be maximum at optimum depth of cut
(iii) Output can be increased by keeping the depth of cut less than optimum depth
(iv) Output can be increased by increasing the size of shovel
select the correct statements?
A. (ii), (iii) and (iv) are correct
B. (i), (ii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i) and (iv) are correct