A. output costing
B. standard costing
C. achieved costing
D. input costing
Advertisement
Related Mcqs:
- The standard input allows one unit, to be divided by standard cost per output unit, for variable direct cost input to calculate ___________?
- A. standard price per input unit B. standard price per output unit C. standard cost per input unit D. standard cost per output unit...
- An actual quantity of input use is multiplied to actual prices, to calculate direct variable manufacturing cost in ________?
- A. actual costing method B. normal costing method C. direct costing method D. indirect costing method...
- The fixed direct manufacturing cost is calculated, by multiplying standard prices for standard quantity of allowed input for actual output in ___________?
- A. input costing B. output costing C. standard costing D. achieved costing...
- The standard cost of allocation base, allowed to output achieved, is multiplied to standard variable overhead rate is to calculate __________?
- A. indirect manufacturing overhead cost B. direct manufacturing overhead cost C. fixed manufacturing overhead cost D. variable manufacturing overhead cost...
- The budgeted variable overhead rate, is multiplied to an actual quantity of allocation base, is to calculate variable manufacturing cost of overheads in ___________?
- A. direct costing method B. indirect costing method C. actual costing method D. normal costing method...
- The difference between actual quantity use and input quantity for output is multiplied with budgeted price to calculate ___________?
- A. efficiency deviation B. efficiency variance C. budgeted variance D. usage variance...
- In the standard costing, the standard quantity allocation is multiplied to standard overhead rates for allocating __________?
- A. flexible costs B. variable costs C. overhead costs D. fixed costs...
- If the budgeted price of input is $50, actual quantity of input is 150 units and the allowed budgeted quantity of input is 60 units then efficiency variance will be __________?
- A. $4,500 B. $3,500 C. $2,500 D. $1,500...
- Considering two years 2013 and 2014, the quantity of output produced in 2014 is divided by cost of input used in 2013, to produce output in 2014 to calculate ___________?
- A. benchmark engineered productivity B. benchmark total factor productivity C. benchmark partial productivity D. benchmark total productivity...
- If the budgeted price of input is $70, actual quantity of input is 250 units and the allowed budgeted quantity of input is 90 units, then efficiency variance will be ___________?
- A. $23,800 B. $11,200 C. $12,200 D. $13,200...
Advertisement