A. sales revenue variance
B. cost profit variance
C. profit volume variance
D. sales volume variance
Advertisement
Related Mcqs:
- The difference between corresponding static budget and flexible budget amount is called ___________?
- A. sales volume variance B. sales mix variance C. sales quantity variance D. market share variance...
- The difference between corresponding static budget and flexible budget amount is called __________?
- A. sales volume variance B. sales mix variance C. sales quantity variance D. market share variance...
- The difference between static budget amount and the flexible budget amount is named as ___________?
- A. sales mix variance B. sales volume variance C. flexible budget variance D. static budget variance...
- The difference between an actual budget and the corresponding amount in static budget is classified as ___________?
- A. correspondent budget B. full budget variance C. methodology variance D. static budget variance...
- The difference between static budget amount and the flexible budget amount is named as ____________?
- A. sales mix variance B. sales volume variance C. flexible budget variance D. static budget variance...
- If the sales budget variance for operating income is $68000 and the static budget amount is $19000, then flexible budget amount will be ____________?
- A. $47,000 B. $57,000 C. $87,000 D. $97,000...
- If the sales budget variance is $57000 and the flexible budget amount is $97000, then the static budget amount will be _____________?
- A. $40,000 B. $154,000 C. $164,000 D. $124,000...
- If the sales budget variance is $47000 and the flexible budget amount is $77000, then the static budget amount will be __________?
- A. $144,000 B. $134,000 C. $124,000 D. $30,000...
- If the sales budget variance for operating income is $58000 and the static budget amount is $15000, then flexible budget amount will be _____________?
- A. $43,000 B. $73,000 C. $63,000 D. $53,000...
- If an actual result is $5500 and corresponding amount of flexible budget on the basis of actual level of output is $3500, then flexible budget variance will be ___________?
- A. $2,500 B. $5,500 C. $3,500 D. $2,000...
Advertisement