A. $60
B. $90
C. $80
D. $70
Advertisement
Related Mcqs:
- If an actual manufacturing overhead costs is $485000 and actual total quantity of cost allocation base is 4500 labor hours, then the overhead rate would be _____________?
- A. 109.87 B. $107.78 C. $106.56 D. $104.34...
- If an actual quantity of cost allocation base is $48000 and budgeted quantity of cost allocation base is $28000, then variable overhead efficiency variance would be __________?
- A. $20,000 B. $76,000 C. $86,000 D. $96,000...
- An actual quantity of cost allocation base is $56000, budgeted quantity of cost allocation base is $17000, then the variable overhead efficiency variance is ___________?
- A. $39,000 B. $49,000 C. $59,000 D. $73,000...
- If the budgeted annual manufacturing indirect cost is $2250000 and the cost allocation base is 2800 labor hour, then budgeted manufacturing overhead rate will be ___________?
- A. $803.571 per labor hour B. $805 per labor hour C. $905 per labor hour D. $802 per labor hour...
- If the budgeted direct labor hours are 3550 and direct labor cost rate is $500 per labor hour, then total direct labor cost would be __________?
- A. $1,775,000 B. $1,675,000 C. $1,875,000 D. $1,975,000...
- If the budgeted direct labor hours are 4550 and direct labor cost rate is $600 per labor hour then, total direct labor cost would be _____________?
- A. $4,730,000 B. $3,730,000 C. $2,730,000 D. $1,730,000...
- Of the cost allocation base, the difference between actual and budgeted variable overhead cost multiplied by actual quantity for actual output is classified as ____________?
- A. variable overhead spending variance B. fixed overhead spending variance C. constant spending variance D. potential spending variance...
- The budgeted variable overhead rate, is multiplied to an actual quantity of allocation base, is to calculate variable manufacturing cost of overheads in ___________?
- A. direct costing method B. indirect costing method C. actual costing method D. normal costing method...
- If an actual variable quantity is 50, the actual and budgeted overhead cost of allocation is $7550 and $4500 respectively, then the variable overhead spending variance could be __________?
- A. $182,500 B. $152,500 C. $162,500 D. $172,500...
- If an actual variable quantity is 70, the actual and budgeted overhead cost of allocation is $8650 and $3500 respectively, then the variable overhead spending variance will be __________?
- A. $660,500 B. $560,500 C. $460,500 D. $360,500...