A. Army method
B. Needle beam method
C. Austrian method
D. English method
Related Mcqs:
- Assertion A : English method of tunneling requires more time as compared to other methods of tunneling. Reason R : In English method of tunneling, the masons and excavators have to work alternately/
A. Both A and R are true and R is the correct explanation of A.
B. Both A and R are true and R is not the correct explanation of A.
C. A is true but R is false.
D. A is false but R is true. - In compressed air tunneling, the volume of free air provided is______________?
A. 6 mJ per second per m2 of face area
B. 6 m3 per minute per m2 of face area
C. 20 m3 per minute per m2 of face area
D. 6 m3 per hour per m2 of face area - The most suitable soil for compressed air tunneling is________________?
A. silt
B. sand
C. clay
D. gravel - In Belgium method of tunneling _________________?
A. construction of side walls is completed before invert and roof arch are built
B. construction of roof arch is completed before side walls and invert are built
C. construction of invert is completed before side walls and roof arch are built
D. construction of invert and side walls is completed before roof arch is built - Which of the following lining material is useful for shield driven tunnels in sub aqueous regions ?
A. stone masonry
B. timber
C. cast iron
D. cement concrete - The correct sequence of drilling equipment for increasing size of holes in tunnels is________________?
A. wagon drill, churn drill, shot drill
B. wagon drill, shot drill, churn drill
C. shot drill, churn drill, wagon drill
D. churn drill, wagon drill, shot drill - Drift method of tunnelling is used to construct tunnels in__________________?
A. soft grounds
B. rock
C. self supporting grounds
D. broken grounds - Ribs are used for strengthening and stiffening the liner plate for tunnels of diameter greater than_____________________?
A. 2 m
B. 3 m
C. 4 m
D. 5 m - Circular section of tunnels is not suitable for________________?
A. carrying water
B. non-cohesive soils
C. tunnels driven by shield method
D. placement of concrete lining - In “full face” method of constructing tunnels, the first operation relates to______________?
A. removal of bottom portion
B. excavation of one drift in the centre
C. removal of top portion
D. excavation being done along the periphery