A. reduced work
B. spoilage
C. rework
D. scrap
Related Mcqs:
- If the manufacturing cycle efficiency is 0.725 and the total manufacturing time is 45 minute, then the value added manufacturing time will be _________?
A. 42.625
B. 36.724
C. 32.625
D. 41.625 - If the value added manufacturing time is 65 minutes, the total manufacturing time is 80 minutes, then the manufacturing cycle time will be _________?
A. 0.8125
B. 0.6125
C. 0.9125
D. 1.725 - The reduction in setup time, manufacturing cycle efficiency and average time of manufacturing for key products are the examples of ____________?
A. measures of growth and learning
B. measures of internal business processes
C. customer measures
D. financial measures - The direct manufacturing labor costs is added into manufacturing overhead cost to calculate ___________?
A. transaction costs
B. conversion costs
C. resale costs
D. merchandise costs - In throughput costing, the variable manufacturing overhead and direct manufacturing labor cost must be treated as ___________?
A. accrual cost
B. incurred cost
C. period costs
D. setup costs - If the fixed budgeted manufacturing cost is $35000 and the budgeted production units are 7000, then budgeted fixed manufacturing cost per unit will be ___________?
A. $20
B. $5
C. $10
D. $15 - If the budgeted annual manufacturing indirect cost is $2250000 and the cost allocation base is 2800 labor hour, then budgeted manufacturing overhead rate will be ___________?
A. $803.571 per labor hour
B. $805 per labor hour
C. $905 per labor hour
D. $802 per labor hour - The package which consists of two or more products to be sold for single price, but components of products in package have separate stand-alone price is called ___________?
A. step down product
B. dual mix product
C. bundled product
D. reciprocal product - An engineering of products or detailed planning of products or services is called ___________?
A. product design
B. research steps
C. useful chain
D. value added - If the direct material cost is $5500 and the prime cost is $25000, then the direct manufacturing labor would be ___________?
A. $19,500
B. $30,500
C. $45,500
D. $22,500