A. 1.5 m 3
B. 2.0 m3
C. 4.0 m2
D. 5.0 m2
Related Mcqs:
- The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is ________________?
A. 1.00 m3
B. 1.25 m3
C. 1.50 m3
D. 1.75 m3 - The expected out turn of cement concrete 1 : 2 : 4 per mason per day is_________________?
A. 1.5 m 3
B. 2.5 m3
C. 3.5 m3
D. 5.0 m3 - The expected out turn of 2.5 cm cement concrete floor per mansion per day__________________?
A. 2.5 sqm
B. 5.0 sqm
C. 7.5 sqm
D. 10 sqm - The expected out turn for earth work in excavation in ordinary soil per workman per day is_______________?
A. 1.00 cum
B. 2.00 cum
C. 3.00 cum
D. 4.00 cum - The expected out turn of 12 mm plastering with cement mortar is_______________?
A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m - Brick walls are measured in sq. m if the thickness of the wall is_________________?
A. 10 cm
B. 15 cm
C. 20 cm
D. None of these - The item of the brick structure measured in sq.m, is___________________?
A. Reinforced brick work
B. Broken glass coping
C. Brick edging
D. Brick work in arches - For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is___________________?
A. 0.200 m3
B. 0.247 m3
C. 0.274 m3
D. 0.295 m3 - In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and_________________?
A. Breadth of the wall
B. Half breadth of wall on each side
C. One fourth breadth of wall on each side
D. None of these - As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken________________?
A. 1.80 litres for 5 to 10 users
B. 1.20 litres for 15 users
C. 1.35 for 20 users
D. All the above