A. 10 cm
B. 15 cm
C. 20 cm
D. None of these
Related Mcqs:
- In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and_________________?
A. Breadth of the wall
B. Half breadth of wall on each side
C. One fourth breadth of wall on each side
D. None of these - The expected out turn of half brick partition wall per mason per day is___________________?
A. 1.5 m 3
B. 2.0 m3
C. 4.0 m2
D. 5.0 m2 - The brick work is not measured in cu m in case of_______________?
A. One or more than one brick wall
B. Brick work in arches
C. Reinforced brick work
D. Half brick wall - The item of the brick structure measured in sq.m, is___________________?
A. Reinforced brick work
B. Broken glass coping
C. Brick edging
D. Brick work in arches - The brick work is measured in sq metre, in case of_________________?
A. Honey comb brick work
B. Brick flat soling
C. Half brick walls or the partition
D. All the above - The concrete work for the following part of the building of specified thickness is measured in square metres_______________?
A. Root slabs
B. Floors
C. Wall panels
D. All the above - The item of steel work which is measured in sq.m, is_________________?
A. Collapsible gates
B. Rolling shutters
C. Ventilators and glazing
D. All the above - For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is___________________?
A. 0.200 m3
B. 0.247 m3
C. 0.274 m3
D. 0.295 m3 - The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is ________________?
A. 1.00 m3
B. 1.25 m3
C. 1.50 m3
D. 1.75 m3 - The weight of an item is measured correct to nearest_________________?
A. 0.25 kg
B. 0.50 kg
C. 0.75 kg
D. 1.00 kg