A. identify the activities which can be delayed without affecting the total float of preceding activity
B. identify the activities, which can be delayed without affecting the total float of succeeding activity
C. establish priorities
D. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Related Mcqs:
- In the critical path method of construction planning, Free Float can be_____________?
Consider the following statements ?
1. greater than Total Float.
2. greater than Independent Float
3. equal to Total Float.
4. less than Independent Float. Of these statementsA. 1 and 4 are correct
B. 2 and 3 are correct
C. 1 and 4 are correct
D. 1 and 2 are correct - Free float for any activity is defined as the difference between__________________?
A. its earliest finish time and earliest start time for its successor activity
B. its latest start time and earliest start time
C. its latest finish time and earliest start time for its successor activity
D. its earliest finish time and latest start time for its successor activity - Whenever an activity has zero total float, then_______________?
A. free float of the activity must be zero but independent float need not be zero
B. independent float must be zero but free float need not be zero
C. free float and independent float both must be zero
D. free float and independent float both need not be zero - Interfering float is the difference between__________________?
A. total float and free float
B. total float and independent float
C. free float and independent float
D. none of the above - The independent float affects only_______________?
A. preceding activities
B. succeeding activities
C. the particular activity involved
D. none of the above - Total float for any activity is defined as the difference between________________?
A. its latest finish time and earliest start time for its successor activity
B. its latest start time and earliest start time
C. its latest start time and earliest finish time
D. its earliest finish time and earliest start time for its successor activity - The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to_________________?
A. 2 kg/tonne
B. 6 kg/tonne
C. 9 kg/tonne
D. 20 kg/tonne - Grader is used mainly for___________________?
A. trimming and finishing
B. shaping and trimming
C. finishing and shaping
D. finishing, shaping and trimming - PERT technique of network analysis is mainly useful for__________________?
A. small projects
B. large and complex projects
C. research and development projects
D. deterministic activities - If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is________________?
A. 4 days
B. 6 days
C. 10 days
D. 16 days