A. Moist loam
B. Sand and gravel
C. Good common earth
D. Wet sticky clay
Related Mcqs:
- If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be_________________?
A. equal to X
B. more than X
C. less than X
D. any of the above - Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing Reason R: If the angle of swing is decreased, the cycle time will be decreased_______________?
A. Both A and R are true and R is the correct explanation of A
B. Both A and R are true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true - The reduction in project time normally results in_______________?
A. decreasing the direct cost and increasing indirect cost
B. increasing the direct cost and decreasing the indirect cost
C. increasing the direct cost and indirect cost both
D. decreasing the direct cost and indirect cost both - For which of the following materials, the output of power shovels for a fixed shovel size will be maximum_______________?
A. Moist loam
B. Good common earth
C. We|l blasted rock
D. Wet sticky clay - For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is__________________?
A. 8 days
B. 9 days
C. 10 days
D. 15 days - Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
A. on commencement of work at site for payment of loan taken by him
B. for the purchase of construction materials
C. for the payment of advances to labour and other staff
D. for all activities required to start the work at site on finalization of the contract document - Which of the following does not represent an activity?
A. site located
B. foundation is being dug
C. the office area is being cleaned
D. the invitations are being sent - The process of incorporating changes and rescheduling or replanning is called_______________?
A. resource levelling
B. resource smoothening
C. updating
D. critical path scheduling - Sinking fund is_______________?
A. the fund for rebuilding a structure when its economic life is over
B. raised to meet maintenance costs
C. the total sum to be paid to the municipal authorities by the tenants
D. a part of the money kept in reserve for providing additional structures and structural modifications - The basic action involved in sheep foot rolling is_______________?
A. Kneading
B. Pressing
C. Tamping
D. Vibration