A. trimming and finishing
B. shaping and trimming
C. finishing and shaping
D. finishing, shaping and trimming
Related Mcqs:
- Free float is mainly used to_________________?
A. identify the activities which can be delayed without affecting the total float of preceding activity
B. identify the activities, which can be delayed without affecting the total float of succeeding activity
C. establish priorities
D. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities - PERT technique of network analysis is mainly useful for__________________?
A. small projects
B. large and complex projects
C. research and development projects
D. deterministic activities - Select the incorrect statement?
A. A critical path always begins at the very first event
B. A critical path always terminates at the last event
C. Critical activities control the project duration
D. Critical activity is the one for which free float is zero - The normal time required for the completion of project in the above problem is_______________?
A. 9 days
B. 13 days
C. 14 days
D. 19 days - For which of the following materials, the output of power shovels for a fixed shovel size will be maximum_______________?
A. Moist loam
B. Good common earth
C. We|l blasted rock
D. Wet sticky clay - A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels : 25000 kg Scraper wheels : 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is_______________?
A. 10000 kg
B. 12500 kg
C. 22500 kg
D. 5000 kg - For excavating utility trenches with precise control of depth, the excavation equipment used is_______________?
A. Hoe
B. Shovel
C. Dragline
D. None of the above - Preliminary project report for a road project must contain___________________?
A. the detailed estimated cost based on detailed design
B. the several alternatives of the project that have been considered
C. the soil survey, traffic survey, concept design and approximate cost
D. the contract documents for inviting tenders - If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________________?
A. 50%
B. less than 50%
C. more than 50%
D. 100% - The direct cost of a project with respect to normal time is________________?
A. minimum
B. maximum
C. zero
D. infinite