A. Smooth-wheeled rollers
B. Vibratory rollers
C. Sheep foot rollers
D. Tampers
Related Mcqs:
- Which one of the following is not an excavating and moving type of equipment ?
A. Bulldozer
B. Clam shell
C. Scraper
D. Dump truck - An earth moving equipment costs Rs. 5,00,000/- and has an estimated life of 10 years and a salvage value of Rs. 50,000/-.What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069 ?
A. Rs. 31050
B. Rs. 34500
C. Rs. 37950
D. Rs. 50000 - For excavating utility trenches with precise control of depth, the excavation equipment used is_______________?
A. Hoe
B. Shovel
C. Dragline
D. None of the above - The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be________________?
A. Rs. 8,800/-
B. Rs. 7,600/-
C. Rs. 6,400/-
D. Rs. 5,000/- - A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be________________?
A. Rs.1740
B. Rs.3480
C. Rs.5220
D. Rs.6960 - Which of the following excavators is most suitable for digging under water?
A. Drag line
B. Hoe
C. Clam shell
D. Dipper shovel - If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is_________________?
A. 500 cum
B. 1000 cum
C. 1500 cum
D. 2000 cum - The probability of completion of any activity within its expected time is_________________?
A. 50%
B. 84.1%
C. 99.9%
D. 100% - In the network shown in Fig. (15 fig) the latest start time of an activity 4-5 is_________________?
A. 2
B. 4
C. 8
D. 7 - Updating may result in_________________?
A. change of critical path
B. decrease of project completion time
C. increase of project completion time
D. all of the above