A. is always longest
B. is always shortest
C. may be longest
D. may be shortest
Related Mcqs:
- In the critical path method of construction planning, Free Float can be_____________?
Consider the following statements ?
1. greater than Total Float.
2. greater than Independent Float
3. equal to Total Float.
4. less than Independent Float. Of these statementsA. 1 and 4 are correct
B. 2 and 3 are correct
C. 1 and 4 are correct
D. 1 and 2 are correct - In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?
A. longest duration
B. highest cost slope
C. least cost slope
D. shortest duration - Which of the following does not represent an activity?
A. site located
B. foundation is being dug
C. the office area is being cleaned
D. the invitations are being sent - Select the incorrect statement?
A. A critical path always begins at the very first event
B. A critical path always terminates at the last event
C. Critical activities control the project duration
D. Critical activity is the one for which free float is zero - If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be_________________?
A. equal to X
B. more than X
C. less than X
D. any of the above - In resources levelling________________?
A. total duration of project is reduced
B. total duration of project is increased
C. uniform demand of resources is achieved
D. cost of project is controlled - Batching refers to________________?
A. controlling the total quantity at each batch
B. weighing accurately, the quantity of each material for a job before mixing
C. controlling the quantity of each material into each batch
D. adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch - Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
A. on commencement of work at site for payment of loan taken by him
B. for the purchase of construction materials
C. for the payment of advances to labour and other staff
D. for all activities required to start the work at site on finalization of the contract document - For a given size of bucket, the ideal output of a dragline will be least in_______________?
A. Moist loam
B. Sand and gravel
C. Good common earth
D. Wet sticky clay - The direct cost of a project with respect to normal time is________________?
A. minimum
B. maximum
C. zero
D. infinite