A. 0.43 d
B. 0.55 d
C. 0.68 d
D. 0.85 d
Related Mcqs:
- According to Whitney’s theory, depth of stress block for a balanced section of a concrete beam is limited to_______________?
A. 0.43 d
B. 0.537 d
C. 0.68 d
D. 0.85 dwhere d is effective depth of beam[ES 2k]
- As per Whitney’s theory, the maximum moment of resistance of the balanced section of a beam of width b and effective depth d is given by_______________?
A. ^acybd2
B. ^acybd2
C. 0.185acybd2
D. 0.43acybd2
where acy is the cylinder compressive strength of concrete - If the depth of actual neutral axis in a beam is more than the depth of critical neutral axis, then the beam is called________________?
A. balanced beam
B. under-reinforced beam
C. over-reinforced beam
D. none of the above - A continuous beam is deemed to be a deep beam when the ratio of effective span to overall depth (1/D. is less than__________________?
A. 1.5
B. 2.0
C. 2.5
D. 3.0 - If the permissible stress in steel in tension is 140 N/mm2, then the depth of neutral axis for a singly reinforced rectangular balanced section will be___________________?
A. 0.35 d
B. 0.40 d
C. 0.45 d
D. dependent on grade of concrete also - If the depth of neutral axis for a singly reinforced rectangular section is represented by kd in working stress design, then the value of k for balanced section_______________?
A. depends on as, only
B. depends on aCbC only
C. depends on both crst and acbc
D. is independant of both ast and acbc where d is the effective depth, ast is per-missible stress in steel in tension and ocbc is permissible stress in concrete in bend¬ing compression - For a simply supported beam of span 15m, the minimum effective depth to satisfy the vertical deflection limits should be________________?
A. 600 mm
B. 750 mm
C. 900 mm
D. more than 1 m - For a cantilever of effective depth of 0.5m, the maximum span to satisfy vertical deflection limit is______________?
A. 3.5 m
B. 4 m
C. 4.5 m
D. 5 m - In working stress design, permissible bond stress in the case of deformed bars is more than that in plain bars by_______________?
A. 10%
B. 20%
C. 30%
D. 40% - If nominal shear stress tv exceeds the design shear strength of concrete xc, the nominal shear reinforcement as per IS : 456-1978 shall be provided for carrying a shear stress equal to__________________?
A. xv
B. xc
C. xv – TC
D. Tv + Tc