A. degree of possibility
B. degree of average
C. degree of variance
D. degree of freedom
Related Mcqs:
- All the conditions or assumptions of regression analysis in simple regression can give __________?
A. dependent estimation
B. independent estimation
C. reliable estimates
D. unreliable estimates - The Regression Analysis Method of quantitative analysis of cost function considers ____________?
A. all data points
B. One data point
C. Two data points
D. Four data points - The worse fit between estimated cost and actual observations is shown on regression line with ___________?
A. larger residual terms
B. zero residual terms
C. variable residual terms
D. smaller residual terms - The cost analysis method, which uses mathematical method to use fit between past data observations and cost functions is termed as ___________?
A. quantitative analysis method
B. qualitative analysis method
C. account analysis method
D. conference analysis method - A technique which minimizes sum of squared vertical difference, to determine the regression line is considered as _____________?
A. negative square technique
B. positive square technique
C. least square technique
D. most square technique - In cost accounting, the conference, quantitative analysis and account analysis methods are considered as __________?
A. cost estimation methods
B. price estimation methods
C. unit estimation method
D. variable estimation method - In Regression Analysis, the testing of assumptions if these are true or not is classified as ___________?
A. weighted analysis
B. average analysis
C. significance analysis
D. specification analysis - The standard error of regression analysis is known as ____________?
A. average of coefficient
B. variance of residual
C. mean of residual
D. average of residual - In Regression Analysis, if an observed cost value is 85 and the disturbance error is 25 then predicted cost value will be ___________?
A. 110
B. 125
C. 60
D. 70 - In Regression Analysis, if an observed cost value is 85 and the disturbance error is 25 then predicted cost value will be ___________?
A. 95
B. 50
C. 120
D. 100